You have an SAP production landscape in Azure that contains an SAP HANA database.

You need to configure a Recovery Services vault that will be used to back up the HANA database server. The solution must ensure that the virtual machine and the HANA database can be restored manually to a paired region.

What should you do first?

  • A. Create a Recovery Services vault in the paired region.
  • B. Enable Cross Region Restore.
  • C. Configure zone-redundant storage (ZRS) replication for the storage.
  • D. Create a recovery plan.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
25max
2 months, 1 week ago
Selected Answer: B
https://learn.microsoft.com/en-us/azure/backup/backup-create-recovery-services-vault#set-cross-region-restore
upvoted 1 times
...
DA_SAP_Basis
9 months, 3 weeks ago
Selected Answer: B
As one of the restore options, Cross Region Restore (CRR) allows you to restore SAP HANA databases that are hosted on Azure VMs in a secondary region, which is an Azure paired region. https://learn.microsoft.com/en-us/azure/backup/sap-hana-database-restore#cross-region-restore
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago