You are building the Bill of materials (BOM) for a new production item. The new item has a subcomponent.
Subproduction orders for the subcomponent must be created when estimating production orders.
You need to configure the BOM line to generate subproduction orders.
Which BOM line type should you use?

  • A. Vendor
  • B. Item
  • C. Phantom
  • D. Pegged supply
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Yugene
Highly Voted 7 months ago
D is correct. 1. https://learn.microsoft.com/en-us/dynamics365/supply-chain/production-control/bill-of-material-bom 2. https://learn.microsoft.com/en-us/dynamicsax-2012/appuser-itpro/about-line-types
upvoted 5 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...