DRAG DROP -
A company uses distributed hybrid topology within their Dynamics 365 Supply Chain Management system.
The company plans to build a manufacturing plant on a mountain to be closer to a required mineral source. Internet connectivity is unreliable, and availability of bandwidth speed is limited. The company plans to deploy an operational edge scale unit for the plant to address the connectivity issue.
You need to determine where production operations can be performed.
Which method should you recommend?
To answer, drag the appropriate methods to the correct requirements. Each method may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content.
NOTE: Each correct selection is worth one point.

Show Suggested Answer Hide Answer
Suggested Answer:

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Kechka
Highly Voted 5 months, 2 weeks ago
• Production floor execution interface and Warehouse Management mobile app • Warehouse Management mobile app • Production floor execution interface
upvoted 14 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago