exam questions

Exam MB-335 All Questions

View all questions & answers for the MB-335 exam

Exam MB-335 topic 1 question 34 discussion

Actual exam question from Microsoft's MB-335
Question #: 34
Topic #: 1
[All MB-335 Questions]

A company produces pipe at certain fixed lengths.
The company must be able to schedule cutting machines. You set up the cutting machines as resources. All cutting resources can produce many of the products. There are some products that cutting machines that can produce longer lengths of product. Only some of the machines can do this.
You need to configure the resources to account for these different products.
What should you do?

  • A. Build capability related to length and assign to the appropriate resources.
  • B. Configure the Data/Hour option on the Capacity unit field on the resource.
  • C. Create a resource for each length.
  • D. Create a resource group for each length.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Tonheidie
Highly Voted 1 year ago
Selected Answer: A
Capabilities - A capability is the ability of a resource to perform a given activity that is relevant to production. Capabilities are assigned to an operations resource. A resource can have more than one capability assigned to it, and a capability can be assigned to more than one resource.
upvoted 6 times
...
globeearth
Most Recent 2 months ago
Selected Answer: A
A. Build capability related to length and assign to the appropriate resources. - you can define resource capabilities to specify the abilities of each resource (cutting machine). By creating a capability related to the length of the product (e.g., "Long Length Cutting"), you can assign this capability only to the machines that can produce longer lengths. This allows the system to schedule production based on the specific capabilities of each machine, ensuring that only compatible machines are selected for jobs requiring longer lengths.
upvoted 1 times
...
lgv0000
3 months, 1 week ago
Selected Answer: A
Resource capabilities 100%
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...