A manufacturing company is implementing production in Dynamics 365 Supply Chain Management.

The production scheduler requires that machines not be scheduled to run concurrently when planning production. The scheduler also must be able to see the scheduling in a graphical view.

You need to configure the system to meet the requirements.

Which three options should you configure? Each answer presents a partial solution.

NOTE: Each correct selection is worth one point.

  • A. bottleneck resource
  • B. finite capacity
  • C. operations scheduling
  • D. job scheduling
  • E. Capable to Promise
Show Suggested Answer Hide Answer
Suggested Answer: ABD 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
juan1603
11 months, 3 weeks ago
Selected Answer: ABD
ABD is correct
upvoted 3 times
...
MEK93
1 year ago
Selected Answer: ABD
It's definitely not C because the graphical view (Gantt) is only active at job scheduling. And E Capable to promise is not relevant here.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...