exam questions

Exam MB-335 All Questions

View all questions & answers for the MB-335 exam

Exam MB-335 topic 1 question 26 discussion

Actual exam question from Microsoft's MB-335
Question #: 26
Topic #: 1
[All MB-335 Questions]

HOTSPOT -
A bicycle manufacturing company is implementing Dynamics 365 Supply Chain Management.
The warehouse must pick and stage parts other than paint for bicycle assembly. Paint is at the production station.
You need to configure the reservations for production.
What should you configure? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.

Show Suggested Answer Hide Answer
Suggested Answer:

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
b8c2f82
2 months, 3 weeks ago
Define the reservation principle for paint: You should set the reservation principle to Start. This means that inventory is reserved when production starts3. This way, you can ensure that paint is available at the production station when needed
upvoted 1 times
...
4cc52dd
8 months ago
Answer is correct. In the Item model group, under inventory policies, you can activate the override item production reservation and set to manual. Since the paint should always be available at the production location, it should never require picking work. https://learn.microsoft.com/en-us/dynamics365/supply-chain/production-control/override-default-reservation-principle#:~:text=On%20the%20other%20hand%2C%20if%20you%20have%20materials%20or%20ingredients%20that%20don%27t%20require%20pick%20work%2C%20because%20they%20are%20consumed%20directly%20from%20a%20location%2C%20you%20typically%20select%20the%20manual%20reservation%20principle%2C%20which%20doesn%27t%20make%20any%20physical%20reservations%20or%20generate%20any%20pick%20work.
upvoted 1 times
...
Rikkert020
11 months, 2 weeks ago
I find the question very unclear, but first one should be production order in my opinion. Not sure about the second one.
upvoted 2 times
CCexamn
11 months ago
Looks like we don't want to reserve the paint since it is already on the production location ready to be consumed. We must reserve the other parts in the warehouse. Since reservation on the production order will give all BOM lines same reservation principle we can’t reserve on production order. Therefore, Question A must be Item model group, B Manual.
upvoted 1 times
Deetss
11 months ago
I agree with CCexamn per: https://learn.microsoft.com/en-us/dynamics365/supply-chain/production-control/override-default-reservation-principle
upvoted 2 times
...
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel