Actual exam question from Microsoft's PL-600
Question #: 29
Topic #: 3
[All PL-600 Questions]

A customer plans to use Microsoft Power Platform integration capabilities to migrate its on-premises sales database to Microsoft Dataverse. The database has more than 10 years of sales data with complex table relationships. The data is used to generate real-time sales reports and predictive analytics.

The customer requires a data migration strategy that implements the following:

• ensures minimal downtime
• maintains data integrity
• allows for validation of migrated data before switching to the new system
• ensures that the historical data is preserved accurately in the Dataverse environment

Which two strategies should you use? Each correct answer presents part of the solution.

NOTE: Each correct selection is worth one point.

  • A. Perform a full migration and start using Dataverse after migration.
  • B. Perform a full migration and perform a test run on Dataverse to simulate real-time activity.
  • C. Develop a phased migration plan in which data is moved in chunks based on years.
  • D. Map the data schema to Dataverse and validate integrity through trial loads.
  • E. Migrate historical data to Azure Data Lake to reduce migration complexity.
Show Suggested Answer Hide Answer
Suggested Answer: BD 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
loftuscheek
3 months ago
Selected Answer: CD
Correct answer CD, however it can do problems with relationships but the question mention minimal downtime
upvoted 1 times
...
WASSIM2020
5 months ago
Selected Answer: BD
B,C,D are correct but i go for B & D because they are more importantes for migration data
upvoted 3 times
...
DivyaAlias
6 months ago
Selected Answer: BD
BD is the right answer
upvoted 2 times
...
HX
6 months, 1 week ago
Selected Answer: CD
the provided as it allows minimizes downtime by allowing you to move smaller sets of data in stages, instead of all at once. Before performing a full migration, mapping the schema to Dataverse ensures that all relationships, data types, and dependencies are accounted for.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...