Question #: 19
Topic #: 6
[All MB-330 Questions]

HOTSPOT -
A company uses Dynamics 365 Supply Chain Management for master planning in manufacturing processes.
Master planning runs have increased in processing time over the past month.
You need to identify the impact of configuration changes on performance from a single location.
Which objects should you use? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.
Hot Area:

Show Suggested Answer Hide Answer
Suggested Answer:
Reference:
https://docs.microsoft.com/en-us/dynamics365/supply-chain/master-planning/tasks/monitor-master-planning-run

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
globeearth
5 months ago
[1] Gant chart - From the "View master planning progress" page, you can view details of historical master planning runs as a Gantt chart. This functionality can help you understand the time that is spent on the various phases of master planning. [2] Colors - If you view a master planning job that is currently running, progress is shown through colors in the Gantt chart. The following colors apply to the blue theme. For other color themes, the colors will differ. Dark blue – Completed planning tasks. Orange – The task that is currently in progress. Light blue – The estimate for remaining tasks.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...