Actual exam question from Microsoft's MB-330
Question #: 48
Topic #: 6
[All MB-330 Questions]

HOTSPOT
-

A company runs master planning in Dynamics 365 Supply Chain Management.

The company wants to move to Planning Optimization for improved performance and efficiencies.

You need to configure the system to stop master planning and begin Planning Optimization.

What should you do? To answer, select the appropriate options in the answer area.

NOTE: Each correct selection is worth one point.

Show Suggested Answer Hide Answer
Suggested Answer:

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
globeearth
1 month, 2 weeks ago
[d]. Use the Lifecycle Services add-in.- To enable Planning Optimization, you must install and connect the Planning Optimization Add-in through Microsoft Dynamics Lifecycle Services (LCS). [b] . Delete and recreate the batch jobs. - Existing master planning batch jobs are configured for the legacy engine and won’t automatically use Planning Optimization after the switch.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel