You are a project manager for an organization that is using Microsoft Project.
You have enabled Single Entry Mode and team members update their task using timesheets.
You need to see how these updates impact your project before you approve the tasks.
What should you do?

  • A. From Project Professional Backstage view, review updates.
  • B. From Project Professional Tracking Gantt, review updates.
  • C. From Project Professional Task Usage, review updates.
  • D. Go to the PWA Approvals page and run the rules you have configured.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
MT202020
4 years, 11 months ago
Should be A? From the Project Professional Backstage you can click on View Task Updates, which brings you to the PWA Approvals page, where you can then select task updates and click on Preview Updates. It cannot be D because when you run the rules, it applies the changes without preview.
upvoted 1 times
...
PGt
5 years, 1 month ago
I think that the correct answer must be: Go to the PWA Approvals page, select task updates and click on preview updates
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...