DRAG DROP -
Your company uses Project Professional 2013.
You are a program manager in charge of a multi-program software integration project. The project is scheduled from January 1, 2012-August 3, 2013. You have a consultant resource that charges a different rate based on each task completed. Tasks 1 through 9 are billed at a rate of $150.00 per hour. Tasks 10 through 20 are billed at a rate of $175.00 per hour.
You need to set up your schedule to ensure that the correct resource rate is associated with the correct tasks.
Which two actions should you perform in sequence? (To answer, move the appropriate two actions from the list of actions to the answer area and arrange them in the correct order.)
Select and Place:

Show Suggested Answer Hide Answer
Suggested Answer:
Note:
* You can model these more complex billing schemes by using rate-table features in Project:
1. Right-click the resource, and from the list select Information.
2. On the Resource Information dialog, click the Costs tab.
3. In the Cost rate tables, click the A (Default) tab.
4. In the Effective Date column, enter the date when the rate change takes effect.
5. In the Standard Rate and Overtime Rate columns, type the resource rates.
6. To enter a rate change that takes place on another date, in the additional rows of the cost rate tables, type or select the new date, and the new standard rates and overtime rates.
7. To enter additional sets of pay rates for the same resource, click the B tab, and then repeat steps 3-5.
Reference: Enter costs for resources

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Currently there are no comments in this discussion, be the first to comment!
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago