Actual exam question from Microsoft's 74-343
Question #: 23
Topic #: 1
[All 74-343 Questions]

You are a project manager who uses Project Professional 2013.
All resources in your project schedule have availability of 8 hours per day. You notice that several of the resources on the project are overallocated. You decide to level the project to help resolve the overallocations for the resources.
Team members often do not work at the same time when completing their work on the tasks.
You need to resolve the overallocations by using the Resource Leveling function.
What should you do?

  • A. Click the Level only within available slack option.
  • B. Click Clear Leveling.
  • C. Click the Leveling can adjust individual assignments on a task option.
  • D. Click the Level resources with a proposed booking type option.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Currently there are no comments in this discussion, be the first to comment!
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...