Actual exam question from Microsoft's 70-348
Question #: 5
Topic #: 1
[All 70-348 Questions]

Your organization is using Microsoft PPM to manage large projects. Within the Microsoft PPM environment, you use SharePoint sites with task lists to manage smaller projects. You turn on the Timesheets feature.
You must collect information about the time that resources spend on all projects.
You need to ensure that you can capture timesheet data from the existing SharePoint task lists.
Which two actions will achieve the goal? Each correct answer presents a complete solution.

  • A. Convert the SharePoint task lists into an enterprise project.
  • B. Use the Get Started with Project Web App web part to add existing SharePoint task lists to Project Center.
  • C. Activate the enterprise project features for the SharePoint sites.
  • D. In Project Center, add existing SharePoint task lists to PWA as a project.
  • E. In SharePoint, add existing SharePoint task lists to Project Center.
Show Suggested Answer Hide Answer
Suggested Answer: AC 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Currently there are no comments in this discussion, be the first to comment!
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...