You are utilizing the Microsoft Solution Framework (MSF) for Agile Software Development 6.0 process template.
You need to track progress for the current sprint.
Which three actions should you perform? (Each correct answer presents part of the solution. Choose three.)

  • A. Review team capacity.
  • B. From the Product Backlog view of the current sprint, review the By Work capacity bars for each contributor.
  • C. Review the task board.
  • D. Review the burndown chart.
  • E. From the project portal, review the Iteration Backlog spreadsheet.
Show Suggested Answer Hide Answer
Suggested Answer: ADE 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Currently there are no comments in this discussion, be the first to comment!
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...