You are using the Microsoft Visual Studio Scrum 2.0 process template. You recently finished a sprint. You need to conduct a retrospective meeting prior to planning the next sprint. What should you do?
A.
Analyze and revise the story points of the work items completed in the previous sprint.
B.
Analyze the previous sprint to identify what the team is going to do differently during the next sprint.
C.
Analyze items in the product backlog for the next sprint.
D.
Determine which items have been finished on the previous sprint.
Currently there are no comments in this discussion, be the first to comment!
This section is not available anymore. Please use the main Exam Page.70-498 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Comments