Actual exam question from Microsoft's MB-320
Question #: 12
Topic #: 2
[All MB-320 Questions]

You are the production planner for a manufacturing company.
After running operations scheduling for a production order, the following error message displays:

You need to identify the cause of the error.
Which two actions should you perform? Each correct answer presents part of the solution.
NOTE: Each correct selection is worth one point.

  • A. Navigate to the work calendar and view working times. Validate that there are working days created in the scheduled period.
  • B. Review the calendar for the resource to determine if it is expired.
  • C. Review the available resources for Operation 10. Navigate to the Resource form and validate whether there is a calendar assigned.
  • D. Review the resource group assigned to Operation 10. Check to see if there is a calendar assigned and if the calendar is expired.
Show Suggested Answer Hide Answer
Suggested Answer: CD 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Moribund
Highly Voted 4 years, 11 months ago
Operations scheduling uses the resource group - unless a single resource is specifically is added to the route operation
upvoted 7 times
...
aouwendijk
Most Recent 3 years, 6 months ago
Selected Answer: CD
For operations scheduling you can connect an operation to either a resource or a resource group. So you must review both resource and resource group for a work calendar with open working times.
upvoted 4 times
...
Sanguru
4 years, 1 month ago
I would go to AD, as the error is for Operations scheduling no resources are involved yet
upvoted 4 times
...
ZVV
4 years, 3 months ago
So it should be BD https://docs.microsoft.com/en-us/dynamics365/supply-chain/production-control/operations-scheduling
upvoted 1 times
ZVV
4 years, 3 months ago
>> The sum of available capacity on the resources that are involved determines the capacity for the resource group. Probably I was wrong - BC is correct
upvoted 3 times
Alexpet
3 years, 7 months ago
B is correct if you know the calendar assigned to the resource. C is correct as per total capacity on resources. A is incorrect because it doesn't cover the resource. D is incorrect because on this screen we are looking at a production order not the route in general: however, this too can be an issue I believe. The provide answer of BC is probably correct.
upvoted 3 times
...
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.