Question #: 32
Topic #: 1
[All 70-768 Questions]

DRAG DROP -

Case Study #1 -
This is a case study. Case studies are not limited separately. You can use as much exam time as you would like to complete each case. However, there may be additional case studies and sections on this exam. You must manage your time to ensure that you are able to complete all questions included on this exam in the time provided.
To answer the questions included in a case study, you will need to reference information that is provided in the case study. Case studies might contain exhibits and other resources that provide more information about the scenario that is described in the case study. Each question is independent of the other question on this case study.
At the end of this case study, a review screen will appear. This screen allows you to review your answers and to make changes before you move to the next sections of the exam. After you begin a new section, you cannot return to this section.

To start the case study -
To display the first question on this case study, click the Next button. Use the buttons in the left pane to explore the content of the case study before you answer the questions. Clicking these buttons displays information such as business requirements, existing environment, and problem statements. If the case study has an
All Information tab, note that the information displayed is identical to the information displayed on the subsequent tabs. When you are ready to answer a question, click the Question button to return to the question.

Background -
Wide World Importers imports and sells clothing. The company has a multidimensional Microsoft SQL Server Analysis Services instance. The server has 80 gigabytes (GB) of available physical memory. The following installed services are running on the server:
✑ SQL Server Database Engine
✑ SQL Server Analysis Services (multidimensional)
The database engine instance has been configured for a hard cap of 50 GB, and it cannot be lowered. The instance contains the following cubes: SalesAnalysis,
OrderAnalysis.
Reports that are generated based on data from the OrderAnalysis cube take more time to complete when they are generated in the afternoon each day. You examine the server and observe that it is under significant memory pressure.
Processing for all cubes must occur automatically in increments. You create one job to process the cubes and another job to process the dimensions. You must configure a processing task for each job that optimizes performance. As the cubes grown in size, the overnight processing of the cubes often do not complete during the allowed maintenance time window.

SalesAnalysis -
The SalesAnalysis cube is currently being tested before being used in production. Users report that day name attribute values are sorted alphabetically. Day name attribute values must be sorted chronologically. Users report that they are unable to query the cube while any cube processing operations are in progress. You need to maximize data availability during cube processing and ensure that you process both dimensions and measures.

OrderAnalysis -
The OrderAnalysis cube is used for reporting and ad-hoc queries from Microsoft Excel. The data warehouse team adds a new table named Fact.Transaction to the cube. The Fact.Transaction table includes a column named Total Including Tax. You must add a new measure named Transactions Total Including Tax to the cube. The measure must be calculated as the sum of the Total Including Tax column across any selected relevant dimensions.

Finance -
The Finance cube is used to analyze General Ledger entries for the company.

Requirements -
You must minimize the time that it takes to process cubes while meeting the following requirements:
✑ The Sales cube requires overnight processing of dimensions, cubes, measure groups, and partitions.
✑ The OrderAnalysis cube requires overnight processing of dimensions only.
✑ The Finance cube requires overnight processing of dimensions only.
You need to create the cube processing job and the dimension processing job.
Which processing task should you use for each job? To answer, drag the appropriate processing tasks to the correct locations. Each processing task may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content.
Select and Place:

Show Suggested Answer Hide Answer
Suggested Answer:
Box 1: ProcessData -
Processes data only without building aggregations or indexes. If there is data is in the partitions, it will be dropped before re-populating the partition with source data.

Box 2: Process Update -
Forces a re-read of data and an update of dimension attributes. Flexible aggregations and indexes on related partitions will be dropped.
References:https://docs.microsoft.com/en-us/sql/analysis-services/multidimensional-models/processing-options-and-settings-analysis-services

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
othman_ee
4 years, 4 months ago
1. Process Data 2. Process Update
upvoted 3 times
...
clement_
4 years, 5 months ago
My Answer: Process Add Process Update Since when does "Process Data" is considered "incremental" ? The docs for it says ". If there is data is in the partitions, it will be dropped before re-populating the partition with source data."
upvoted 1 times
...
Cococo
4 years, 6 months ago
Let's do it one by one: Clear - no Update - only for Dimensions - second box Index - not enough Add - doesn't work for Cubes Data - more or less (it is not going to add indexes and aggregations) Structure - "If the cube is unprocessed, Analysis Services will process, if it is necessary, all the cube's dimensions". This will not process measures. Looks like there should be another option, something like Default...
upvoted 1 times
Cococo
4 years, 6 months ago
There is a chance that the answer for the Cube is simple - Incremental? - process add, and you can deploy and process all new changes manually, don't need to do this every day..
upvoted 1 times
Cococo
4 years, 6 months ago
sorry, Process Data :) Add is not for cubes
upvoted 1 times
...
...
...
julie2020
4 years, 7 months ago
What is the correct answer for this question?
upvoted 1 times
...
Jrestrepo
4 years, 10 months ago
For the Incremental cube processing job, the processing task should be "Process Structure" (because there were structural changes done to both the "Sales Analysis" and the the "Order Analysis" cubes. And for the "Incremental dimension processing" job, the processing task should be "Process Add" (Because it adds new members, and a measure was created). Any thoughts? For measure groups and partitions, adds newly available fact data and process only to the relevant partitions.
upvoted 1 times
Cococo
4 years, 6 months ago
"SalesAnalysis cube ... You need to maximize data availability during cube processing and ensure that you process both dimensions and measures." Process structure for cubes will not touch the measures.
upvoted 1 times
...
...
Jrestrepo
4 years, 10 months ago
Is it me, but these questions are so not fair. Are they using the terms: "Processing tasks" and "Processing Options" interchangebly? Looking at this questions closely, there were structural changes done to the "Order Analysis" cube (a new table and measure was added). The case also states that the "Sale Analysis" cube was being tested. In both these case you would use "Process Full", which by the way is not on the list of "Processing task" given.
upvoted 1 times
...
Jrestrepo
4 years, 10 months ago
Both jobs can use "process data", right?
upvoted 1 times
CYRUSD
4 years, 10 months ago
For Dimension, And to have it updated faster. I believe Process Update is correct.
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago