Exam MB-320 topic 3 question 47 discussion

Actual exam question from Microsoft's MB-320
Question #: 47
Topic #: 3
[All MB-320 Questions]

A manufacturing company uses master planning in Dynamics 365 Supply Chain Management.

The production planner increases the lead time of an item. On the next master planning output, the planner receives a cancel action message on existing purchase orders. The message includes a suggested earlier date for the planned purchase orders.

The demand for the item has not changed since the original purchase order was placed. Dynamic negative days is not used.

You need to resolve the issue.

What should you do?

  • A. Increase positive days.
  • B. Decrease negative days to be less than the item lead time.
  • C. Decrease positive days.
  • D. Increase negative days to be greater than the item lead time.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
boxafrica
2 weeks, 1 day ago
Selected Answer: C
I'm arriving at C by process of elimination.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...