Question #: 29
Topic #: 1
[All MB-320 Questions]

A company produces multiple products that require an installation kit that includes 50 components.
The company does not want to include these 50 components in every Bill of materials (BOM). You have a BOM kit that includes all 50 components, but you do not want it to produce a separate production order.
You need to set up the product BOM for the finished good.
What should you do?

  • A. Select Phantom on the engineering fast tab on the kit item
  • B. Change the coverage group on the kit item to Manual
  • C. Change the line type to Phantom
  • D. Change the line type to Pegged supply
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
eimsis
4 years ago
C is correct, Question indicates You need to set up the PRODUCT BOM for the finished good. so on the BOM the Kit Line item type can be Phantom
upvoted 2 times
...
Pir
4 years ago
C is correct. https://docs.microsoft.com/en-us/dynamics365/supply-chain/production-control/phantom-items
upvoted 2 times
Pir
4 years ago
My bad A is more suitable, as then this item whenever included in "every" BOM will turn into phantom line automatically.
upvoted 1 times
viking1
3 years, 10 months ago
True, but the question talks about setting up the BOM for the finished goods, so C is correct here. Doing A first may avoid the need to do this, but it is outside the scope of setting up the BOM for the finished goods.
upvoted 1 times
...
...
...
ZVV
4 years, 3 months ago
I believe A is more reasonablehttps://community.dynamics.com/ax/b/msdynaxlessonslearned/posts/phantoms https://community.dynamics.com/365/financeandoperations/b/kurthatlevik/posts/ax-2012-kitting-revisited
upvoted 2 times
ElAndo
4 years, 1 month ago
Yes, also there is no option at the line of a Formula (just None, Filler, Compensating and Active) to set the item as phantom. You set it first (and only) as phantom in the Engineering tab. When you launch a production order for another item that includes said phantom, the production order explodes the article and it's components are shown in the production BOM.
upvoted 2 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...