Exam MB-320 topic 2 question 5 discussion

Actual exam question from Microsoft's MB-320
Question #: 5
Topic #: 2
[All MB-320 Questions]

Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some questions sets might have more than one correct solution, while others might not have a correct solution.
After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.
A manufacturing plant uses Lean processes. You plan to outsource a painting operation to a subcontracting vendor. You create a service item named SP-01 to represent the painting service.
You need to create a subcontracting activity for the painting service.
Solution:
✑ Create a vendor resource and work cell for outsourced painting; add the vendor resource to the work cell.
✑ Create a production flow process activity using the painting work cell and the service item for picking.
✑ When the service is required, create a purchase order to the subcontracting vendor and add a line for the service item and the vendor price.
Does the solution meet the goal?

  • A. Yes
  • B. No
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️
References:
https://docs.microsoft.com/en-us/dynamics365/unified-operations/supply-chain/production-control/activity-based-subcontracting

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ZVV
4 years, 3 months ago
Don't we need to create purchase agreement first and link it to the activity?
upvoted 4 times
Daichisan
3 years, 6 months ago
Yeah i would say so
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...