DRAG DROP -
You need to set up the system to calculate the overhead rates automatically for production.
Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
Select and Place:

Show Suggested Answer Hide Answer
Suggested Answer:
Set up and configure manufacturing

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ZVV
Highly Voted 4 years, 3 months ago
You can't assign cost group directly to resources - you need to assign it to cost category instead. https://docs.microsoft.com/en-us/dynamics365/supply-chain/cost-management/cost-groups https://docs.microsoft.com/en-us/dynamics365/supply-chain/cost-management/cost-categories-used-production-routings
upvoted 5 times
Alexpet
3 years, 7 months ago
In that case it should be: 1. Create cost groups. 2. Create price total and cost group nodes on costing sheet. 3. Create overhead calculation node to materials as surcharge and labor as rate for setup time. 4. Define the basis for calculating cost as absorption.
upvoted 1 times
...
...
Daichisan
Most Recent 3 years, 7 months ago
4,5,7,2 should be correct
upvoted 2 times
...
ElAndo
4 years, 1 month ago
I think the answer is: 4. Create cost groups 7. Create price total and cost group nodes on costing sheet 2. Create overhead calculation node for materials as surcharge and labor as rate for setup time 5. Associate cost groups to items and cost categories
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...