Question #: 18
Topic #: 2
[All MB-320 Questions]

Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some questions sets might have more than one correct solutions, while others might not have a correct solution.
After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.
A company implements Dynamics 365 Supply Chain Management for their Lean manufacturing environment.
There has been an engineering change to a fixed quantity product that is in production. This change will add an additional processing step as the second step.
The existing version must be phased out and replaced by the new version.
You need to ensure that the engineering change takes affect at the end of the month.
Solution:
1.) Edit the existing step number two activity to be the new engineering process
2.) Edit the existing production flow. Set the expiration date due to the end of the month
3.) Edit the existing Kanban rule. Set the expiration date to the end of the month
4.) Activate the production flow
Does the solution meet the goal?

  • A. Yes
  • B. No
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Rhennuj
Highly Voted 4 years, 3 months ago
Based from the question it says that "The existing production flow version must be phased out and replaced by the new version" So it means, that you need to create a new production flow version before creating an activity to be added to the new version.
upvoted 5 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...