DRAG DROP -
A company uses Dynamics 365 Process manufacturing.
Employees work a half day so that they can attend a company event. You have a rush order that must be completed that same day.
After reviewing the net requirements of the batch order, only 400 of the total quantity of 1400 units must be completed today. The production manager must retain the original batch number as the quantity of 400. The original batch number must appear on documentation for the customer.
You need to split the batch order onto two orders.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
Select and Place:

Show Suggested Answer Hide Answer
Suggested Answer:

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ElAndo
4 years, 2 months ago
Correct, the value you enter to split corresponds to the new order created, so the first one, in this example, remains to be the 400 they need to do first.
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.