exam questions

Exam MB-320 All Questions

View all questions & answers for the MB-320 exam

Exam MB-320 topic 1 question 45 discussion

Actual exam question from Microsoft's MB-320
Question #: 45
Topic #: 1
[All MB-320 Questions]

A company implements manufacturing in Dynamics 365 Supply Chain Management.
The company wants to efficiently produce products comprised of different order types.
You need to select the appropriate production plan.
Which production process should you use for the production run?

  • A. discrete
  • B. process
  • C. lean
  • D. mixed mode
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️
Reference:
https://docs.microsoft.com/en-us/dynamics365/supply-chain/production-control/production-process-overview

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
viking1
3 years, 9 months ago
Different order types in this context means different types of production, i.e. production orders, batch orders, kanbans. This is called mixed mode manufacturing, though I have also seen "Unified" used instead of "Mixed".
upvoted 3 times
...
sachink4
3 years, 11 months ago
Since this is order specific manufacturing, it should be discrete - A
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago