A company produces pipe at certain fixed lengths.
The company must be able to schedule cutting machines. You set up the cutting machines as resources. All cutting resources can produce many of the products.
There are some products that require cutting machines that can produce longer lengths of product. Only some of the machines can do this.
You need to configure the resources to account for these different products.
What should you do?

  • A. Configure the Data/Hour option on the Capacity unit field on the resource.
  • B. Build capability related to length and assign to the appropriate resources.
  • C. Create a resource group for each length.
  • D. Create a resource for each length.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️
Reference:
https://docs.microsoft.com/en-us/dynamics365/supply-chain/production-control/tasks/define-resource-capabilities

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
viking1
3 years, 10 months ago
Correct. B - Capability.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...