You are a production manager at a company that has implemented lean manufacturing using Dynamics 365 Supply Chain Management.
You have created a new Kanban rule to replace one that is expiring.
You need to determine the impact to the existing process jobs.
How are the active Kanbans of the expired rule handled?

  • A. The active Kanbans are set to add to the requested period and distribute for the replacement rule time fence.
  • B. The active Kanban handling units are registered as empty and new Kanbans are created.
  • C. The active Kanbans are cancelled.
  • D. The active Kanbans are counted as Kanbans of the replaced rule.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
viking1
Highly Voted 3 years, 10 months ago
The answer is incorrect. The correct answer is D. https://docs.microsoft.com/en-us/learn/modules/create-process-fixed-kanbans-dyn365-supply-chain-mgmt/3-rule When a Kanban rule expires, the active Kanbans are counted as Kanbans of the replaced rule. (Poor wording, should be "replacing rule")
upvoted 8 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other