You are configuring project metrics for dashboards in Azure DevOps. You need to configure a chart widget that measures the elapsed time to complete work items once they become active. Which of the following is the widget you should use?
C. Cycle time
A. Cumulative Flow Diagram shows the number of work items in different states over time and can be used to monitor progress and identify bottlenecks, but it doesn't specifically measure elapsed time.
B. Burnup charts show the progress of completed work items over time and can be used to measure progress towards a goal, but it doesn't measure elapsed time once work items become active.
D. Burndown charts show the remaining work over time and can be used to measure progress towards completing a set of work items, but it doesn't measure elapsed time once work items become active.
Cycle time, on the other hand, specifically measures the elapsed time from when a work item becomes active to when it is completed, making it the best option to fulfill the requirement in the question.
#chatgpt
"Lead time is calculated from Work Item Creation to entering a Completed state.
Cycle time is calculated from first entering an In Progress or Resolved state category to entering a Completed state category."
Also check the related diagram, that is very explanatory.
https://learn.microsoft.com/en-us/azure/devops/report/dashboards/cycle-time-and-lead-time?view=azure-devops
"The burndown and burnup widgets give you flexibility to create charts for any type of scope or number of teams in specified time periods. Burndown charts focus on remaining work. Burnup charts focus on completed work. Both chart types help your team determine whether you're on track to complete your work by the end date."
https://learn.microsoft.com/en-us/azure/devops/report/dashboards/configure-burndown-burnup-widgets?view=azure-devops
C is the answer.
https://learn.microsoft.com/en-us/azure/devops/report/dashboards/cycle-time-and-lead-time?view=azure-devops
Both lead time and cycle time widgets are useful to teams. They both indicate how long it takes for work to flow through their development pipeline. Lead time measures the total time elapsed from the creation of work items to their completion. Cycle time measures the time it takes for your team to complete work items once they begin actively working on them.
This section is not available anymore. Please use the main Exam Page.AZ-400 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Certs4Future_com
Highly Voted 2 months, 2 weeks agoCubbywoo
Highly Voted 7 months agoTolahap
Most Recent 1 week, 4 days agof3a93c1
2 weeks agoMo_alwaysjolling
1 month, 3 weeks agoDeepu_s
3 months, 3 weeks agozellck
7 months agokarimullah
8 months agoChandraSingh
1 year, 5 months agokleansoul
1 year, 7 months agoMsds1981
1 year, 9 months agoRangnath
2 years agosampath918
2 years agoRealnaijaguy
2 years, 2 months agopandji
2 years, 5 months agonhannn
2 years, 5 months agoHg6421
2 years, 5 months ago