All employees at a company work eight hours each day Monday through Friday. A resource named Resource1 has 40 hours available for a specific week.
You need to schedule Resource1 to work on a project during that week. The resource must work the hours detailed below:
Which allocation method should you use?
cindy100X
11 months, 4 weeks agofmontez
2 years, 1 month agodizzle83
2 years, 2 months ago