You are the Microsoft Project Server administrator for your company. You have recently upgraded the hardware of your Microsoft Project Server farm. You and the project managers in your company believe that it will be much faster. You have now created performance logs to measure the throughput of the new server configuration to compare to past performance. What is this process called?

  • A. Performance baseline creation
  • B. Step funding
  • C. Before and after snapshot
  • D. Performance measurement
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
sbcmonteur
Highly Voted 5 years, 8 months ago
Correct answer must be D.
upvoted 7 times
...
PatrickH
Most Recent 3 years, 4 months ago
You need something to compare to. That is called a baseline. You cannot say anything is faster or slower if you dont have something to compare it to. So its A.
upvoted 3 times
...
Essi
4 years, 1 month ago
How do we know if it's faster if we have nothing to compare with? Therefore A is the correct Baselin.
upvoted 3 times
...
Timock
4 years, 5 months ago
A baseline for your performance measure is the average level of performance that you are currently at, and that you will compare future performance levels with to test if performance is really changing. As per the question they are asking what the creation is called. Its called a performance level baseline.
upvoted 3 times
...
vbhatt84
4 years, 5 months ago
answer is most definitely D. As you would be comparing it. it would only be A if it was a fresh install with nothing to compare it to. hence Baseline. but stick with D on the actual exam if it comes up.
upvoted 1 times
...
johnnybravo
4 years, 6 months ago
Surely the correct answer is D. If it was "What is the first step" A would be correct. The fact the question already establishes you have done this “You have now created performance logs to measure the throughput… “ and are looking to compare those results with the new ones, “new server configuration to compare to past performance” clearly shows the baseline has been created and anything after is Performance and Monitoring how the new system and set up compares.
upvoted 1 times
...
Cazaciuc
4 years, 7 months ago
It should be D. IF the question was what`s the FIRST process to do, then, answer would be A. But as a whole, it`s D
upvoted 1 times
...
steranto
4 years, 11 months ago
Anyway you're creating a new baseline at last, so A is considered correct
upvoted 4 times
...
Diogof786
4 years, 11 months ago
I don't know which one it is, I'm dumb and I have no idea what it's all about, good afternoon.
upvoted 4 times
...
Aim9lima
4 years, 12 months ago
You have now created performance logs(this is the process you carried out) to measure the throughput of the new server configuration to compare to past performance(This is the reason you carried it out). What is this process called?(The question is about the process, not the reason) Correct answer is A. It is a deceptive question containing extraneous information.
upvoted 4 times
...
felcar0817
5 years, 1 month ago
Baseline, A
upvoted 4 times
...
LTTAM
5 years, 4 months ago
It mentions ‘compare to past performance’. The correct answer should be ‘D’. Baseline creation would be for a completely NEW set up.
upvoted 2 times
...
Sugar
5 years, 5 months ago
A is the answer here. first you need to have a baseline for measurement. once you have that, then the measurement process will follow
upvoted 3 times
...
david_jpb
5 years, 6 months ago
I also believe the answer is D. For me creating a baseline it's when i take the first measurements to compare with something else in the future. It it did not mention that it was to make a comparison to the old server I would go with A.
upvoted 1 times
MrMcJohn
4 years, 4 months ago
It's say's: To measure the throughput of the new server configuration to compare to past performance. So it's to make a comparison to the old server.
upvoted 3 times
...
...
WaldoWhereAmI
5 years, 6 months ago
D could be correct, if A wasn't an option. The more accurate answer is Baseline Creation, since you are dealing with a NEW system that you are generating the first report for.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.