Question #: 412
Topic #: 1
[All AZ-900 Questions]

Your company has an Azure subscription that contains several resources.

You need to identify which department is responsible for the cost of each resource.

What should you use?

  • A. budgets
  • B. alerts
  • C. tags
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
IrvinDitz
Highly Voted 1 year, 11 months ago
Selected Answer: C
I don't see how budgets can help with identifying, I'd go with tags.
upvoted 31 times
nicdun
1 year, 11 months ago
same here, couldn't figure out how budgets where you can control costs in azure can identify resources - if you add them it could be, but tags are perfect for identifying resources.
upvoted 4 times
...
...
sadeemchohan
Highly Voted 1 year, 11 months ago
Just passed my exam today. Scored 925. ALL of the questions were from these dumps. Try to memorize the answers and read the discussions. Good Luck!
upvoted 17 times
yosri_c_sharp
1 year, 11 months ago
did you answer A in this question ?
upvoted 3 times
sadeemchohan
1 year, 11 months ago
this question was not on the exam. but the answer is C. Tags....also there were 33 questions for me. Try to memorize the following questions; 404,405,398,396,394,387,386,382,381,374,347,319,305,303,302,292,291,290,286,275 265 and 266....these are the questions i remember from the exam
upvoted 27 times
...
...
...
liya1
Most Recent 8 months ago
got this question on 22nd
upvoted 1 times
...
hit_cloudie
1 year, 2 months ago
A,C,D is the correct answer.
upvoted 1 times
...
DimsumDestroyer
1 year, 4 months ago
Selected Answer: C
Tags can be used for drilling down into costs.
upvoted 1 times
...
robertirob
1 year, 6 months ago
Selected Answer: C
I agree with tags.
upvoted 1 times
...
Parti
1 year, 6 months ago
tags: C
upvoted 1 times
...
navid1365
1 year, 6 months ago
Selected Answer: C
You should tag the resources with a cost center
upvoted 1 times
...
Eagrob_11
1 year, 6 months ago
can you change the answer please
upvoted 2 times
...
BeauChateau
1 year, 9 months ago
Selected Answer: C
C. tags To identify which department is responsible for the cost of each resource in an Azure subscription, you can use tags. Tags are name-value pairs that enable you to categorize resources in a way that is meaningful to your organization. You can use tags to identify resources that belong to a specific department or project, for example. Once you have tagged your resources with the appropriate department or project information, you can use the Azure Cost Management + Billing service to generate reports and analyze costs by department or project. This can help you identify areas where you may be able to reduce costs or optimize your resource usage. Budgets and alerts can also be useful tools for monitoring and managing costs in an Azure subscription, but they are not specifically designed for identifying which department is responsible for the cost of each resource.
upvoted 2 times
...
JohannesV
1 year, 9 months ago
Selected Answer: C
Agree C
upvoted 1 times
...
Rashica
1 year, 10 months ago
Selected Answer: C
we need to identify which department is responsible, that is done by tags
upvoted 1 times
...
HakimNY
1 year, 11 months ago
and is Tags
upvoted 1 times
...
Vick98
1 year, 11 months ago
Selected Answer: C
it should be C, tags are used for this
upvoted 2 times
...
MoneyStacking
1 year, 11 months ago
Mensen van Goodzo. Wij hebben gehaald!
upvoted 2 times
...
kazan
1 year, 11 months ago
Selected Answer: C
Tags is the answer
upvoted 2 times
...
PowerBastard
1 year, 11 months ago
Selected Answer: C
C. Tags
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...