Question #: 77
Topic #: 1
[All CPCM Questions]

In solicitation planning activity of Contract Management Process, what will be the input by using standard forms as a tool and whose output will be procurements documents?

  • A. Qualified seller list
  • B. Work results
  • C. Market conditions
  • D. Procurement management plan
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Currently there are no comments in this discussion, be the first to comment!
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...