After an onsite cluster deployment, a consultant prepares the deliverables for a project closeout. Which two data in the As-Built Guide require adjustment or might be missing completely? (Choose two.)
✅ C. Nutanix Node Port Layout
This includes how network ports are cabled to switches.
Often differs from pre-install assumptions and may be undocumented unless manually verified.
Needs to be updated to reflect actual port usage and switch connections.
✅ D. Physical Rack Layout
Racking and cabling can change during installation.
Final positions of nodes, switches, and cables often differ from the original design and require on-site verification and documentation.