After an onsite cluster deployment, a consultant prepares the deliverables for a project closeout.
Which two data in the As-Built Guide require adjustment or might be missing completely? (Choose two.)

  • A. Cluster Information
  • B. AHV Host Information
  • C. Nutanix Node Port Layout
  • D. Physical Rack Layout
Show Suggested Answer Hide Answer
Suggested Answer: BC 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
KillerDre
3 weeks, 3 days ago
Selected Answer: CD
✅ C. Nutanix Node Port Layout This includes how network ports are cabled to switches. Often differs from pre-install assumptions and may be undocumented unless manually verified. Needs to be updated to reflect actual port usage and switch connections. ✅ D. Physical Rack Layout Racking and cabling can change during installation. Final positions of nodes, switches, and cables often differ from the original design and require on-site verification and documentation.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...