Question #: 71
Topic #: 1
[All 1z0-964 Questions]

Your customer wants a project start date to cascade to the project tasks, but does not want the finish date to be cascaded. Identify the default setup in a project template that can be used to enable this. (Choose the best answer.)

  • A. Cascade change to the start date.
  • B. Do not cascade date changes.
  • C. Cascade change to the finish date.
  • D. Cascade change to the start date and the finish date.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️
Reference -
http://docs.oracle.com/cd/E25054_01/fusionapps.1111/e20384/F552279AN65801.htm

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Pasha
5 years, 4 months ago
A How to change and save 'Cascade Option' in Project Template ( 'Edit Basic Information') ? (Doc ID 1966295.1)
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel