A supply plan has just been run that contains a configured item. You notice that the sourcing rules of the base model were used instead of sourcing rules for the configured item. Why did this happen?
A.
No planning percentages were defined at the operation level within the work definition.
B.
The sourcing rules of the base model had a priority of 1, while the sourcing rules of the configured item had a priority of 2.
C.
It is not possible to create sourcing rules for the configured item; all configured items always use the same sourcing rules as the base model.
D.
No sourcing rules have been defined for the configured item.
E.
The sourcing rules of the base model overrode the sourcing rules of the configured item.