You want to export your project plan to Oracle Project Financial Management Cloud after initial scheduling is complete in Microsoft Projects. Identify three conditions that must be met for exporting milestone tasks. (Choose three.)
A.
only one labor resource assignment with 100 effort
B.
lowest-level tasks set up with non-zero duration
C.
lowest-level tasks set up with zero duration
D.
only one labor resource assignment with 0 effort
E.
percent work complete values of 0 or 100 percent
Currently there are no comments in this discussion, be the first to comment!
This section is not available anymore. Please use the main Exam Page.1z0-964 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Comments