Select three statements about the submission of invoices by suppliers using Supplier Portal.

  • A. A supplier can submit a single invoice against multiple purchase orders across different currencies and organizations.
  • B. A supplier can submit invoices against open, approved, standard, or blanket purchase orders that are not fully billed.
  • C. A supplier can validate the invoice after submitting it.
  • D. A supplier can submit a single invoice against multiple purchase orders, provided the currency and organization for all the invoice items are the same as those on the purchase orders.
  • E. A supplier can not make changes to the invoice after submitting it.
Show Suggested Answer Hide Answer
Suggested Answer: BDE 🗳️
Reference -
https://docs.oracle.com/cd/E18727_01/doc.121/e13414/T463223T463232.htm

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
SH69
5 years ago
Answers: B D E
upvoted 1 times
...
Yasas
5 years ago
You can submit an invoice online to the buying company based on the purchase order lines you have fulfilled. You need to only identify those items shipped and enter a quantity. You can invoice against open, approved, standard, or blanket purchase orders that are not fully billed. You can enter a credit memo against a fully billed purchase order (use negative quantity amounts to enter a credit memo), as well as invoice against multiple purchase orders. However, the currency and organization of all items on an invoice must be the same. The organization is the entity within the buyer’s company that you are invoicing. You can also partially complete an invoice, save it, and submit it later. After you submit an invoice, you cannot change the invoice. If you need to make adjustments to a submitted invoice, you can create a credit memo against the same purchase order items to net out the invoice charges. The purchase order will then be available for a new invoice.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...