In Projects, which is NOT a valid option for Contract project revenue recognition? Choose the best answer.

  • A. Monthly, Quarterly, or Semiannually
  • B. After Completion
  • C. When Paid
  • D. When Billed
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️
Reference:
https://docs.oracle.com/en/cloud/saas/planning-budgeting-cloud/epbug/GUID-AECB4021-59B2-4C88-AFEE-92FB04D92C21.pdf
(5-6)

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
jprmartinho
3 years, 7 months ago
C is correct https://docs.oracle.com/en/cloud/saas/planning-budgeting-cloud/epbug/GUID-AECB4021-59B2-4C88-AFEE-92FB04D92C21.pdf 5-11
upvoted 1 times
...
Orakle
4 years, 2 months ago
The only thing I can think of here is that it does not make accounting sense. You don't pay for revenue if you are the contractor, you can recognize the obligation for the payee, and then recognize as per the highlighted methods.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...