Question #: 115
Topic #: 1
[All 1z0-060 Questions]

Which three resources might be prioritized between competing pluggable databases when creating a multitenant container database plan (CDB plan) using Oracle
Database Resource Manager? (Choose three.)

  • A. Maximum Undo per consumer group
  • B. Maximum Idle time
  • C. Parallel server limit
  • D. CPU
  • E. Exadata I/O
  • F. Local file system I/O
Show Suggested Answer Hide Answer
Suggested Answer: CDE 🗳️
http://docs.oracle.com/database/121/ADMIN/dbrm.htm#ADMIN11852

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Blade69
3 years, 6 months ago
B - could also be correct Explanation: http://docs.oracle.com/database/121/ADMIN/dbrm.htm#ADMIN11852 D - CPU E - Exadata I/O C - Parallel Execution Server Runaway Queries Active Session Pool with Queuing Undo Pool B - Idle Time Limit - You can specify an amount of time that a session can be idle, after which it is terminated.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...