An administrator accidentally closed the commit window/screen before the commit was finished. Which two options could the administrator use to verify the progress or success of that commit task? (Choose two.) A. B. C. D.
A & D are correct, also you can use the command 'show jobs all' and find the commit job, then you could use 'show jobs id <id>' to show only that commit job process.
AD
trashboat is correct.
Can't be B as that's just traffic logs and C is interface info.
upvoted 2 times
...
This section is not available anymore. Please use the main Exam Page.PCNSE Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
trashboat
Highly Voted 3 years, 6 months agoMarshpillowz
Most Recent 9 months, 1 week agokewokil120
1 year, 7 months agolol12
2 years ago