Question #: 64
Topic #: 1
[All PCSAE Questions]

An engineer would like to change an incident's SLA according to the severity field changes.
How can the engineer achieve this task?

  • A. Use a field trigger script
  • B. Use a field display script
  • C. Create a job that queries for incident severity changes
  • D. Change the SLA manually every time the severity changes
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
amkoppad
Highly Voted 3 years, 9 months ago
A is correct
upvoted 9 times
...
Jai_ke
Most Recent 8 months, 2 weeks ago
Selected Answer: A
A field trigger script can be set up to automatically respond to changes in the severity field by updating the SLA based on predefined rules.
upvoted 1 times
...
news088
1 year, 6 months ago
A is correct. https://www.youtube.com/watch?v=UgkEVkdP5iY
upvoted 3 times
...
MarcoS10
2 years ago
Selected Answer: A
A is correct
upvoted 3 times
...
MarcoS10
2 years ago
A is correct
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago