exam questions

Exam PMI-RMP All Questions

View all questions & answers for the PMI-RMP exam

Exam PMI-RMP topic 1 question 28 discussion

Actual exam question from PMI's PMI-RMP
Question #: 28
Topic #: 1
[All PMI-RMP Questions]

A risk is identified early in the project. After six months, it is determined that the risk does not apply to this particular project.
How should the risk be handled by the risk manager?

  • A. Ignore the risk and concentrate only on the pertinent risks.
  • B. Remove the risk from the risk register and inform the project manager that it is no longer valid.
  • C. Close the risk during the next risk board meeting and keep it in the risk register.
  • D. Conduct a risk analysis to determine how an inappropriate risk was formally accepted.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
MikeMarlo
6 months, 2 weeks ago
Selected Answer: B
"It does not apply to this *particular* project". It did not say that "it does not apply to this project anymore". If the risk was an error >> option B If the risk is outdated >> option C
upvoted 1 times
...
_MCV_
11 months, 2 weeks ago
Selected Answer: C
Correct answer for me is C. You should not remove a risk form the risk register but close it instead
upvoted 2 times
...
C is correct as you need to make all stakeholders aware that it is no longer a risk.
upvoted 1 times
...
Azharmak
1 year ago
C for me. Why should an irrelevant risk should be on Risk Register!
upvoted 1 times
...
OMG4567
1 year, 2 months ago
Selected Answer: C
Never remove a risk from the risk register as this will be input for future lessons learned. But you have to close it and return the CR back to the organization.
upvoted 2 times
...
Lunk
1 year, 2 months ago
Selected Answer: C
Just because a probable event didn't happen doesn't mean you can't get valuable lessons learned from it
upvoted 1 times
...
yandasatria
1 year, 4 months ago
Selected Answer: C
1. Standard has it that you don't delete any risk from the register . Also the best answer is to escalate the risk to the appropriate project it may affect. The risk was identified, assessed, and evaluated at the initial instance There may be reasons why the risk does not apply: maybe the scope has been completed or removed but no matter the reason, the risk is closed and still maintained in the register. You can audit a risk register to determine appropriateness. D is used when referring to issues and problems. Like when a risk occurs that was not identified or the actual impact of a risk is greater than the assessed impact or the response did not accurately mitigate or avoid the risk usually where the frequency is very high on the project If a single risk that was not identified occurs, we use work around but where many of them are occurring, we carry out investigations
upvoted 2 times
...
FAAFMT
1 year, 6 months ago
You should never remove risk from the register.. but you could ignore it if it does not occur
upvoted 1 times
...
FAAFMT
1 year, 6 months ago
C is the RIGHT answer
upvoted 2 times
...
RoyalWarrior
1 year, 8 months ago
A is correct. Risks that have been managed, avoided, or are no longer relevant can be removed from the risk register. The associated risk action plans can also be deleted from the risk registers
upvoted 1 times
...
cslnm1
1 year, 9 months ago
D is a better answer.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...