Given the following information:
✑ Activity A takes one week.
✑ Activity B takes three weeks.
✑ Activity C takes two weeks.
✑ Activity D takes five weeks.
✑ Activity A starts at the same time as Activity B.
✑ Activity C follows Activity B and Activity A.
✑ Activity D follows Activity C.
How long will it take to complete the project?