Given the following information:
✑ Activity A takes one week.
✑ Activity B takes three weeks.
✑ Activity C takes two weeks.
✑ Activity D takes five weeks.
✑ Activity A starts at the same time as Activity B.
✑ Activity C follows Activity B and Activity A.
✑ Activity D follows Activity C.
How long will it take to complete the project?

  • A. 8 weeks
  • B. 9 weeks
  • C. 10 weeks
  • D. 11 weeks
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
CraigB83
9 months ago
WAIT god damn AI thats not right, it starts at week 6 and takes 5 weeks, thats 10 weeks not 11 Sorry!!
upvoted 1 times
...
CraigB83
9 months ago
11 weeks: Activity A starts and takes one week. Activity B starts at the same time as Activity A and takes three weeks. So, at the end of Week 3, both A and B are complete. Activity C follows A and B. Since A and B are complete at the end of Week 3, C starts in Week 4 and takes two weeks. So, at the end of Week 5, Activity C is complete. Activity D follows C. Since C is complete at the end of Week 5, D starts in Week 6 and takes five weeks. So, at the end of Week 11, Activity D is complete. Therefore, the total time to complete the project is 11 weeks.
upvoted 2 times
...
Raae
1 year, 4 months ago
Selected Answer: C
C. Planning out the critical path is B>C>D for a total time of 10 weeks
upvoted 2 times
...
ChymKuBoy
1 year, 5 months ago
Selected Answer: C
C for sure 5th week : A, B, C done
upvoted 1 times
...
Hungdv
1 year, 8 months ago
C The sum of the activity durations in the Critical Path is equal to the Project’s Duration; therefore, a delay to any Critical Activity will result in a delay to the Project Completion Date.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago