exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 208 discussion

Actual exam question from PMI's PMP
Question #: 208
Topic #: 1
[All PMP Questions]

A project manager is working on an agile project that is within the scope of a recently announced corporate audit. The project manager was appointed to attend the first meeting with the auditors scheduled for the following week.
What should the project manager do to prepare for the audit?

  • A. Reserve story points for the next iteration if needed.
  • B. Review the project information.
  • C. Ask the development team to provide compliance information.
  • D. Ask for a waiver during the audit.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Schwery
4 months, 3 weeks ago
Selected Answer: B
The correct answer is: B. Review the project information. Explanation: To prepare for the audit, the project manager should ensure they have a thorough understanding of the project's details, progress, and compliance with corporate policies. Reviewing the project information will allow the project manager to address any questions the auditors might have and demonstrate due diligence in managing the project. C. Ask the development team to provide compliance information: While the development team might be a source of technical details, it is the project manager's responsibility to gather and review relevant project information ahead of the audit.
upvoted 2 times
...
Ngho
6 months, 2 weeks ago
B is the right answer
upvoted 2 times
...
6114c29
6 months, 3 weeks ago
Selected Answer: C
C. Ask the development team to provide compliance information.
upvoted 1 times
...
Rehhakles
7 months ago
Selected Answer: B
To prepare for the audit, the project manager should thoroughly review all project information, including documentation, processes, and records of the project's progress and adherence to corporate standards. This review will help the project manager to be well-informed and ready to answer any questions the auditors may have. It will also allow the project manager to identify any potential areas of concern that the auditors might focus on and prepare explanations or corrective actions for those areas.
upvoted 3 times
...
Musaad
1 year, 3 months ago
Selected Answer: C
project information ?? all information this would take forever I would go with C
upvoted 2 times
...
leo9944
1 year, 5 months ago
B. its the first audit meeting
upvoted 2 times
...
Only12go
1 year, 6 months ago
Selected Answer: B
The best option for preparing for an audit is to review all relevant project information to ensure that everything is in order and that the project manager is well-informed about all aspects of the project. This helps the project manager to answer any questions the auditors might have and to demonstrate that the project is being managed effectively.
upvoted 4 times
...
Asakthi
1 year, 9 months ago
C. Ask the development team to provide compliance information.
upvoted 1 times
...
victory108
1 year, 10 months ago
Selected Answer: B
B. Review the project information
upvoted 1 times
...
Islam122
1 year, 10 months ago
Selected Answer: C
his is because the project manager needs to ensure that the project is compliant with all relevant regulations and standards. The development team is responsible for developing the product, so they will have the most up-to-date information on compliance.
upvoted 2 times
...
SteAle
1 year, 10 months ago
Selected Answer: B
I would go with B. The PM should review all the relevant information about the project to get prepared for the audit, not just compliance info.
upvoted 2 times
...
Sumit182
2 years, 1 month ago
Option B To prepare for the audit, the project manager should review all the project information to ensure that the project is in compliance with corporate policies and regulations. This includes reviewing the project scope, budget, schedule, risks, issues, and any other project documentation. The project manager should also review any applicable corporate policies and regulations to ensure that the project is compliant.
upvoted 4 times
...
emelba
2 years, 2 months ago
I would go for C, it's an audit after all, you need information to provide
upvoted 1 times
Sumit182
2 years, 1 month ago
To prepare for the audit, the project manager should review all the project information to ensure that the project is in compliance with corporate policies and regulations. This includes reviewing the project scope, budget, schedule, risks, issues, and any other project documentation. The project manager should also review any applicable corporate policies and regulations to ensure that the project is compliant.
upvoted 1 times
...
...
terryp
2 years, 2 months ago
Selected Answer: C
Would prefer C. Prep for compliance since it is an audit inline with regulatory compliance.
upvoted 1 times
TPObee
2 years, 1 month ago
Where in the question did it say it's a regulatory compliance audit? It just says audit. I believe B is the most appropriate answer.
upvoted 2 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago