A project's risk manager successfully implements the risk management plan and the risk register. Furthermore, the risk analysis and the risk response planning are finalized. All results have been documented, and the project management plan and other project documents have been updated accordingly.
What should the risk manager do next?
Azharmak
6 months, 2 weeks agoRoyalWarrior
1 year, 2 months agoOMG4567
7 months, 3 weeks ago