exam questions

Exam PMI-RMP All Questions

View all questions & answers for the PMI-RMP exam

Exam PMI-RMP topic 1 question 166 discussion

Actual exam question from PMI's PMI-RMP
Question #: 166
Topic #: 1
[All PMI-RMP Questions]


Given the output from the Monte Carlo simulation, what is the probability of a successful completion within the project budget?

  • A. 30% probability of meeting project budget
  • B. 46% probability of meeting project budget
  • C. 56% probability of meeting project budget
  • D. 60% probability of meeting project budget
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Lunk
7 months, 1 week ago
Selected Answer: C
How does this site mess up such simple math?
upvoted 1 times
...
emikhael
1 year, 1 month ago
Selected Answer: C
should be C : because at 50% the estimated cost is $1,635,00 and at 60% the estimated cost is $1,662,000. The total project cost is $1,655,000 which is between 50% - 60%
upvoted 2 times
...
RoyalWarrior
1 year, 1 month ago
Answer should C because at 50% the estimated cost is $1,635,00 and at 60% the estimated cost is $1,662,000. The total project cost is $1,655,000 which is between 50% - 60%
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago