should be C : because at 50% the estimated cost is $1,635,00 and at 60% the estimated cost is $1,662,000. The total project cost is $1,655,000 which is between 50% - 60%
Answer should C
because at 50% the estimated cost is $1,635,00 and at 60% the estimated cost is $1,662,000. The total project cost is $1,655,000 which is between 50% - 60%
upvoted 2 times
...
This section is not available anymore. Please use the main Exam Page.PMI-RMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Lunk
7 months, 1 week agoemikhael
1 year, 1 month agoRoyalWarrior
1 year, 1 month ago