Two weeks prior to the delivery date, a customer changes the business requirements. What should the business analyst do?

  • A. Deliver the existing product and then begin work on the requested changes.
  • B. Ask the developers to implement the changes.
  • C. Trace the requirements and measure the impact of the requested changes on the existing delivery date.
  • D. Schedule a review by the change control board (CCB) to determine next steps.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
alonso93
6 months, 3 weeks ago
Answer is B, because Business Case was made based on business requirements that's why we should meet first because the impact analysis will only be superfluous in this case
upvoted 1 times
...
sheidaei
1 year ago
Selected Answer: C
I think first c then d, and also sometimes CCB meeting isn't mandatory
upvoted 4 times
...
giushki
1 year, 2 months ago
First C: and after D:
upvoted 2 times
...
Kukusha
1 year, 2 months ago
C is the correct one
upvoted 2 times
...
cslnm1
1 year, 2 months ago
C is the right answer.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...