The programming activities of a project were planned to last 35 days per module, but the programming of the first module has taken 45 days.
What should the project manager do?

  • A. Evaluate the situation and identify ways to compress the schedule without impacting baselines.
  • B. Ask the team to work overtime to complete the deliverable on time.
  • C. Submit a change request to the project sponsor to change the schedule.
  • D. Check the scope to verify if there is scope creep and get the project on schedule.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Only12go
Highly Voted 7 months, 1 week ago
Selected Answer: A
A. Evaluate the situation and identify ways to compress the schedule without impacting baselines. When a project experiences a schedule overrun on a specific activity or module, the project manager should first evaluate the situation to understand the root causes of the delay. It's essential to identify potential solutions to compress the schedule without altering the project baselines (scope, cost, and quality). This may involve adjusting resource allocation, optimizing task sequencing, or finding efficiencies in the remaining work to bring the project back on track. Submitting a change request or immediately resorting to overtime should be considered after a thorough evaluation of alternatives to avoid unnecessary impacts on the project.
upvoted 5 times
...
adingmaki
Most Recent 7 months, 2 weeks ago
D. It's basically root cause analysis.
upvoted 1 times
...
Martinussantika
7 months, 4 weeks ago
Selected Answer: A
Answer should be A, the situation already happening, so better to do evaluate it. To look at scope creeps (answer D) is not to related directly on the action for situation
upvoted 2 times
...
victory108
9 months ago
Selected Answer: A
A. Evaluate the situation and identify ways to compress the schedule without impacting baselines
upvoted 2 times
...
SteAle
10 months, 3 weeks ago
Selected Answer: A
step #1 - evaluate the situation and see if there are ways to get the project back on track
upvoted 2 times
...
sanjiiv
1 year, 2 months ago
Selected Answer: D
I think it needs to be reviewed before taking an action
upvoted 2 times
cwilson91
11 months, 3 weeks ago
True, which is why we "Evaluate the situation" A
upvoted 4 times
...
...
rajeshtk
1 year, 2 months ago
Why not D ?
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...