exam questions

Exam PMI-PBA All Questions

View all questions & answers for the PMI-PBA exam

Exam PMI-PBA topic 1 question 63 discussion

Actual exam question from PMI's PMI-PBA
Question #: 63
Topic #: 1
[All PMI-PBA Questions]

Testing on a project has been completed. In order to proceed with deployment, a decision is needed.
Who should the business analyst contact to review the testing results and get approval to proceed with deployment?

  • A. The tester identified in the testing strategy
  • B. The project manager identified in the project charter.
  • C. The project sponsor identified in the scope document.
  • D. The person identified in the RACI matrix.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
giushki
7 months, 2 weeks ago
Selected Answer: D
The business analyst should contact the project stakeholders responsible for approving the deployment to review the testing results and get approval to proceed with deployment. This could include the project sponsor, project manager, technical leads, and any other stakeholders who have the authority to approve the deployment.
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago