Testing on a project has been completed. In order to proceed with deployment, a decision is needed. Who should the business analyst contact to review the testing results and get approval to proceed with deployment?
A.
The tester identified in the testing strategy
B.
The project manager identified in the project charter.
C.
The project sponsor identified in the scope document.
The business analyst should contact the project stakeholders responsible for approving the deployment to review the testing results and get approval to proceed with deployment. This could include the project sponsor, project manager, technical leads, and any other stakeholders who have the authority to approve the deployment.
upvoted 4 times
...
This section is not available anymore. Please use the main Exam Page.PMI-PBA Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
giushki
7 months, 2 weeks ago