exam questions

Exam PMI-PBA All Questions

View all questions & answers for the PMI-PBA exam

Exam PMI-PBA topic 1 question 72 discussion

Actual exam question from PMI's PMI-PBA
Question #: 72
Topic #: 1
[All PMI-PBA Questions]

A business analyst assigned to review test output for a project realizes that an approved requirement has been missed. Which technique could the business analyst have used to ensure that requirements were delivered as stated?

  • A. Use cased
  • B. Requirements management plan
  • C. Traceability matrix
  • D. Work breakdown structure
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
giushki
Highly Voted 1 year, 4 months ago
Selected Answer: C
C. Traceability matrix. A traceability matrix is a tool that links requirements to their origin and traces them throughout the project lifecycle. By using a traceability matrix, a business analyst can ensure that all requirements are accounted for and delivered as stated. If an approved requirement has been missed during testing, the business analyst can trace back to see where the requirement was introduced and take appropriate action to ensure it is implemented.
upvoted 5 times
...
qunfei
Most Recent 1 year, 1 month ago
Selected Answer: C
ONLY RTM
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel