Exam PMI-PBA topic 1 question 75 discussion

Actual exam question from PMI's PMI-PBA
Question #: 75
Topic #: 1
[All PMI-PBA Questions]

A major stakeholder of a project is surprised to learn that a particular requirement was not implemented during the latest launch. The business analyst tells the stakeholder that the requirement status was changed to “deferred”.
What could have prevented the stakeholder from being surprised about the status change?

  • A. The status should have been reviewed prior to project launch.
  • B. The status should have been communicated to all project stakeholders.
  • C. The status should have been updated in the traceability matrix.
  • D. The status should have been communicated to the requirement’s source.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
qunfei
1 year, 1 month ago
Selected Answer: B
Reasonable, the project launch does not mean that all the requirement status need to be fixed, with time, some points maybe have changed into deferred.
upvoted 1 times
...
giushki
1 year, 4 months ago
Selected Answer: B
B. The status should have been communicated to all project stakeholders. In order to prevent stakeholders from being surprised about changes to requirements status, it is important to communicate any changes in a timely and transparent manner. This includes communicating the status change to all relevant stakeholders, updating any relevant documentation (such as the traceability matrix), and ensuring that the requirement’s source is aware of the change. By keeping everyone informed about changes to requirements status, the project team can avoid surprises and ensure that everyone is on the same page.
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...